FIDIC合同条件中约定,因承包商的责任延误竣工时,损害赔偿金为每天1万元,该合同工程的总金额300万元,而承包商竣工工程的合同价为15万元,延期竣工天数30天,合同中还约定最高赔偿限额为20万元,则在工程结算时可折减的误期损害赔偿金为()万元。
A、005B
暂无解析